The culvert under the landing strip of the airport in Gelendzhik City
In 2004 the project of reconstruction of airport in Gelendzhik was launched. Under this project the construction of a new airport complex and new landing strip was prescribed.
Transmost designed the culvert with water discharge of 19.0m/s under the landing strip of the airport.
The structure consists of 380m-long rectangular reinforced concrete culvert with 4.0x2.5m cross section.
At the beginning the sink is placed.
Year of completion: 2007
Year of airport opening: 2010