The combined bridge is designed for road transport and railway, the length of the bridge is 1611.26m. The total length of bridge approaches is 8353.4m. The total length of river crossing structure is 9961.56m.

This bridge has 3x33.0+(63,0+115,5+63,0)m spans and its total length is 351.38m. The width of the bridge is 2x11.5 plus two footpaths 1m-wide each. Superstructures and piers are different for two traffic routes. Three 33m-long spans consist of prestressed reinforced concrete beams.