The length of this overpass is 679.48m. The width is 11.5m with two staff paths 0.75 each wide. The overpass has 16x42m spans.

The superstructure is steel continuous beam with orthotropic deck, located on the horizontal curve with 2010m radius. The solid unites are connected at the upper chords with units of orthotropic deck. Longitudinal and lateral braces are not applicable. Designed cross section has prefabricated solid units, what helped to achieve high quality and speed of assembling.  

This overpass had been completed within approximately one year instead of 3 years as stated in contract.

Year of completion: 2008